By providing your contact information to Rayneshire Realty LLC, your personal information will be processed in accordance with Rayneshire Realty LLC's Privacy Policy. By checking the box(es) below, you expressly consent to receive marketing or promotional real estate communication from Rayneshire Realty LLC in the manner selected by you. For SMS text messages, message frequency varies. Message and data rates may apply. Consent is not a condition of purchase of any goods or services. You may opt out of receiving further communications from Rayneshire Realty LLC at any time. To opt out of receiving SMS text messages, reply STOP to unsubscribe. SMS text messaging is subject to our Terms of Use.

Thank you for your message. I will be in touch with you shortly.

Why Davenport's New Publix Opened While Its Home Depot Still Has No Move-In Date

Drive Highway 27 through Davenport this September and you will pass several active construction sites, one grand opening banner still snapping in the wind, and a stretch of cleared orange grove that has looked exactly the same for over a year. All of it gets filed under the same mental folder: "something's coming." But that folder is doing residents a disservice, because these projects are not on the same clock, and the difference between them tells you something useful about how retail actually gets built along this corridor.

The clearest example: the new Publix at U.S. 27 and Minute Maid Ramp Road 2 opened its doors on June 25, 2026. Meanwhile the Home Depot going up at 27 and Davenport Boulevard only posted its construction bond in July, a few weeks later, with a public-infrastructure deadline that stretches to May 2027. Same highway. Same growth wave. Wildly different distance from a working cash register.

The One That Already Opened

Polk County development records first showed the Publix site plan for U.S. 27 and Minute Maid Ramp Road 2 back in late 2023, when the proposed store measured just over 57,000 square feet with a liquor store and four retail units attached, plus offsite work widening the ramp road and adding a deceleration lane and turn lanes on 27. That is not a small project. It required its own traffic signal work, the same category of infrastructure lift that slows down bigger anchors elsewhere on the corridor.

And yet it opened on schedule this summer, roughly two and a half years after that site plan surfaced. Publix's own newsroom announcement framed the store as part of "the everyday moments that matter" to shoppers in the area, standard language for a grocery opening, but the timeline behind it is the useful part: from filed paperwork to functioning deli counter, the project ran about thirty months.

That number matters because it becomes the yardstick for everything else on this list.

A Bond Is Not an Opening Date

Home Depot's Davenport store first showed up in county records in March 2025, proposed for a 27-acre lot at the northeast corner of 27 and Davenport Boulevard, next to the RaceTrac. The site plan called for a 135,632-square-foot building with entries on both roads and dual turn lanes.

Sixteen months later, in July 2026, Home Depot posted a $2.35 million performance bond covering the roads, drainage, and other infrastructure the project requires. That bond is a real financial commitment, not a rumor, but it is also not a grand opening. It is the guarantee that public improvements get built, backed by Liberty Mutual as surety, with a completion deadline of May 29, 2027, unless Polk County grants an extension.

Here's the comparison that actually helps: Publix reached a similar permitting milestone back in 2023 and still took about two and a half years to open. If Home Depot's path runs anywhere close to that pace from its own March 2025 starting point, residents watching the grading equipment at Davenport Boulevard this fall are more realistically looking at a 2027 opening than a holiday-season one. The bond tells you the county has its guarantee. It does not tell you when the shelves get stocked.

The Timeline That Already Slipped a Season

Just over the county line in neighboring Haines City, the Crossroads Village Center is the largest single project in the pipeline, a 120-acre, Target-anchored development at U.S. 27 and U.S. 17-92. It is worth tracking even from the Davenport side of the line, because it sits on the same commute for a lot of residents and it is already a case study in how these timelines move.

In February 2025, a property flyer for the site listed Phase 1 delivery for "summer 2026." By the time the developer held its groundbreaking ceremony that April, the same Phase 1 was being described in press coverage as finishing "fall 2026," with the developer saying Target "wants" to open by October. That is a real season of drift, documented in two months of coverage on the same phase of the same project, before a single steel beam went up.

The Target itself will be a 147,000-square-foot SuperTarget, Haines City's first, and it sits about eight miles from the existing SuperTarget at Posner Commons in Davenport, so it is a genuine new option rather than a duplicate. But the slipping language between "summer" and "wants to open by October" is the more instructive detail. Developers describe early timelines with more confidence than the construction calendar usually rewards.

Still Just a Site Plan

Elsewhere in Davenport, a few blocks from AdventHealth Heart of Florida hospital, a side-by-side Walmart Supercenter and Sam's Club were announced in April 2025 as a 56-acre project at U.S. 27 and Holly Hill Grove Road 2, just north of Ridgewood Lakes. The stores are planned at 197,798 and 170,818 square feet, with parking for more than 1,500 cars and nine additional outparcels along the highway.

As of that announcement, construction was only "anticipated" to start sometime in 2026. That puts this project a full stage behind Home Depot, which has already reached the bonding step, and multiple stages behind Publix, which is already ringing up customers. One piece of good news for anyone impatient for something to actually open in that stretch: an EōS Fitness is planned just north of the Walmart and Sam's Club site and is slated to open sometime in 2026, well before its much larger neighbors.

What the Corridor Actually Looks Like Right Now

Project Location on 27 Status as of September 2026 What's still ahead
Publix, Shoppes at Citrus Creek Minute Maid Ramp Road 2 Open Nothing, it's operating
EōS Fitness Near Holly Hill Grove Road 2 Under construction Opening expected later in 2026
Home Depot Davenport Boulevard Bond posted, infrastructure deadline set Roads and drainage due by May 29, 2027
Target, Crossroads Village Center Neighboring Haines City Under construction after 2025 groundbreaking Developer targeting October 2026, already revised once from "summer"
Walmart Supercenter and Sam's Club Holly Hill Grove Road 2, near Ridgewood Lakes Construction not yet confirmed to have started No public opening date

A fence line means someone filed paperwork. A bond means someone put money behind a deadline. A groundbreaking ceremony means shovels touched dirt for the cameras. None of those is the same as a delivery truck backing up to a loading dock for the first time, and only Publix has reached that point so far.

Reading the Signs Without Getting Your Hopes Up

For anyone driving this stretch daily and trying to guess what opens next, the order that has actually held up this year is worth remembering:

  1. Grocery-scale projects with a single building and a manageable offsite road package move fastest. Publix's own record, filed to open in about two and a half years, is the benchmark.
  2. A performance bond is a financial guarantee tied to infrastructure, not a grand opening announcement. Home Depot has one now. It still has until May 2027 just for the roads and drainage.
  3. Big mixed-use anchors with multiple phases, like Crossroads Village Center, tend to see their own early timelines slip a season or two before construction catches up, even when the developer stays confident in public statements.
  4. If a company still describes its own start date as "anticipated," as Walmart's did in its 2025 announcement, treat that as the earliest stage of the pipeline, not a countdown.

None of this means the corridor isn't changing. It clearly is, and quickly. It just means the sign on the fence and the receipt in your hand are two very different milestones, and this stretch of Highway 27 currently has exactly one project that's reached the second one.

If you're weighing what this kind of growth means for home values, resale timing, or whether a particular pocket of Davenport is worth watching before the next Publix-style announcement lands, that's a conversation worth having with someone who tracks this corridor for a living. Bianca Janice Williams and the Rayneshire Realty team follow these Highway 27 filings the same way they follow closings. Let's Connect.